Northeast Early College High School / International High School

""

Northeast Early College High School and International High School are co-located and will receive a Phase 1 (of 3-4) modernization as part of the 2022 Bond. The project design is anticipated to begin in fall 2023 and open to students in spring 2028. The Campus Architectural Team, composed of campus staff, parents and community members, will work with the district and project team to determine the scope of the modernization in order to best meet the needs of the students, staff and communities of Northeast and International.

Northeast and International will also receive a secure entry vestibule and improvements to campus systems including, HVAC, electrical, plumbing and roofing repairs as well as a school mental health center and athletic field/locker room upgrades. 

Follow the links to view the campus FAQs in English and Spanish.

Northeast ECHS & International High School logo

Project Status

Project Details

Total Project Budget: $117,856,000

Anticipated Opening Date: January 2028

Trustee: Candace Hunter

Location: 7104 Berkman Dr., Austin, TX 78752

Program Manager: VANIR|STV

Architecture & Engineering: Perkins&Will

Construction: S&P Construction, Inc.

Bond Financials

For in depth financial and project reporting visit our CBOC meetings page. The Board of Trustees appointed volunteer community members to the Community Bond Oversight Committee (CBOC) to ensure that the projects remain faithful to the voter-approved bond program scope of work and to monitor and ensure the bond projects are completed on time, with quality and within budget.


Milestones

Construction Updates

Q3 2026 Updates:
 

Ongoing Activities:

  • Central Plant upgrades and related mechanical-system improvements are underway.
  • Underground hydronic piping is being installed to support updated heating and cooling systems.
  • Campus utility and drainage improvements are continuing in several areas.
  • Roofing repairs and parapet-wall work are underway to address existing conditions and support upcoming renovation work.

Upcoming Activities:

  • Continue summer infrastructure, utility, and roofing work across campus.
  • Advance Central Plant improvements and coordinate required shutdowns and temporary cooling measures.
  • Finalize updated design packages and pricing for the Old Mall renovation and future campus work.
  • Continue evaluating construction phasing and early-access opportunities for portions of the athletic building while minimizing impacts to campus operations and events.

If you’d like more information about the High School Athletic Field Upgrades, click the link to learn more.

More Information

Nathan Neal, Northeast Principal

Leticia Vega, International Principal

Lauren Kajdas, Staff

Kleyder Medina, Staff

Karina Vela, Staff

Raul Rivera, Staff

LaTisha Anderson, Community Member

Deani Flemmings, Parent

Marcela Garcia, Parent

Tom Sullivan, Parent

Sayra Castro, Parent

Veronica Martinez, Parent

Carter York, Parent

Seth Fowler, Staff

Shawn Paul Lahman, Staff

Abdul Mustafa, Staff

Hannah Gehl, Staff

Kyle Olsen, Staff

Odette Rodriguez, Student

Nehevid Rodriguez, Student