Allison Elementary School

""

Circulation Maps:  English      Spanish  

As part of the 2022 Bond, Allison Elementary School has broken ground on a full modernization of the existing campus at its current location. The new building will feature flexible learning spaces to support a variety of learning styles, designed in partnership with the Allison community. Project design began in spring 2023 and the modernized campus is anticipated to open to students in spring 2026. The new building will be built on the same site, immediately to the east of the existing school. During construction, school activities will remain in the existing building.

Follow the links to view the campus FAQs in English and Spanish.

""

Project Status: Modernized

Project Details

Total Project Budget: $56,320,000

Anticipated Opening Date: January 2026

Trustee: Ofelia Zapata

Location: 515 Vargas Rd. Austin, TX 78741

Program Manager: AECOM

Architecture & Engineering: Mckinney York Architects

Construction: Rogers-O’Brien Construction

Bond Financials

For in depth financial and project reporting visit our CBOC meetings page. The Board of Trustees appointed volunteer community members to the Community Bond Oversight Committee (CBOC) to ensure that the projects remain faithful to the voter-approved bond program scope of work and to monitor and ensure the bond projects are completed on time, with quality and within budget.


Milestones

Construction Updates

Q3 2025 Updates:

Completed/Ongoing:

  • Area C: South section of the building - Foundation and grade beams are complete. Mass erection of steel is complete. 2nd floor and roof decking are complete. Exterior stairs are complete. Steel erectors have finished detailing welds and connections. 2nd floor mechanical and electrical rough in will will start in mid-August.  2nd floor concrete pour will happen in mid-August.  Exterior framing and interior framing layout to start in mid-August, and to be followed by interior framing. Overhead MEP (Mechanical, Electrical, and Plumbing) RI starts the end of August.
  • Area B: Mid section of the building - Foundation and grade beams are complete.  Mass erection of steel is complete.  2nd floor and roof decking are complete. Steel erectors to finish detailing welds and connections.  Mechanical and Electrical to start 2nd floor rough in.
  • Area A: North section of the building - Foundation is complete.  Mass erection of the steel is ongoing and will complete in August.  Detailing of steel and connections will finish in August.
  • Site: Roof drain underground rough-in to start early August.  Main electrical transformer rough-in has passed inspection.  Transformer slab to be poured in early August.

More Information

Lupe Molina, Principal

Aracely Cornejo, Staff

Rosemary Miranda, Assistant Principal

Doris Faz, Parent

Melissa Herrera, Staff

Theresa Hunter, Teacher

Hollie Jenkins, Teacher

Samantha Ladwig, Teacher

Antonio Martinez, Teacher

Jose Noe Elias, Parent

Angela Padilla, Parent

Jesse Palacios, Community Member

Sheila Pharis, Community Member

Lisa Ramirez, Staff

Leticia Torres-Antonio, Staff

Adrian Velez, Parent

Roselyn Perez Bouza, Parent

Maria del Carmen Torres, Parent

Mariana Figueroa, Staff